For a lot of people who live in Mareeba and work in Cairns, or who are thinking about making that move, the Kuranda Range Road is the big question. Here’s where things stand.
Cyclone Jasper repairs
The range was badly damaged by Cyclone Jasper in December 2023, and traffic was disrupted for a long time afterwards, with closures, single-lane sections and speed restrictions. By July 2026, Transport and Main Roads had finished works at 30 sites: 25 on the Kuranda Range Road and five on the Kennedy Highway between Kuranda and Mareeba.
The biggest job, the major landslip below the Henry Ross Lookout, has now been repaired, and two-way traffic has been restored on that section. Some work is still to come: TMR says repairs at two sites damaged in early 2025 are due to start in early 2027, site and weather conditions permitting.
Upgrades to come
Separately from the cyclone repairs, the federal and state governments have committed $262.5 million ($210 million federal and $52.5 million state) to a Kuranda Range Road upgrade strategy aimed at reducing unplanned closures. Works that need lane closures will happen after the recovery works are finished, so expect more roadworks before things get easier.
A new Barron River bridge
Separately, the Kennedy Highway bridge over the Barron River near Kuranda is being replaced. Construction is expected to start in 2028, with the new bridge due to open in 2031.
What it means if you’re buying in Mareeba
Commuting over the range is part of life for many Mareeba households, and it’s a trade-off plenty of people are happy to make for more land and better value than they’d get in Cairns. More roadworks are still to come, but a safer, more reliable road and a new bridge are good long-term news for anyone living up here.
Always check the QLDTraffic website before you travel, especially while works and night closures are under way.
Sources
- Transport and Main Roads: Kuranda Range Road safety and resilience upgrades
- Transport and Main Roads: Kuranda Range Road cyclone reconstruction works
- Queensland Reconstruction Authority: Upgrades to strengthen safety and resilience on Kuranda Range Road
- The Express: October completion date for Kuranda Range Road landslip (14 July 2026)
- Transport and Main Roads: Barron River Bridge (Kuranda) replacement
- QLDTraffic: live road conditions